Skip to main content
Home
Home

Data Centers and Adjacent Generation: What Clients Ask and What Actually Protects Uptime

Data Centers and Adjacent Generation: What Clients Ask and What Actually Protects Uptime

Electrical Transmitting Lines

Data centers depend on clean, fast, and predictable power. 

When onsite or adjacent generation supports that load—whether natural gas, battery, solar plus storage, or hybrid plants—the engineering, procurement, and construction (EPC) choices you make determine whether IT workloads stay online during utility events and peak windows. The questions below come up in nearly every deal and directly affect uptime, power quality at the point of common coupling (PCC), and operability during “critical windows” for the data center.

Snapshot

Sponsors and EPCs are focused on four data center critical fronts:

  • Delivery model. How to assign risk and accountability so power shows up when the data center needs it.
  • Uptime guarantees. Metrics that protect critical windows and power quality at the PCC, not just nameplate capacity.
  • Schedule discipline. Keeping energization on track despite utility reviews and long-lead equipment.
  • OT security baselines. Cyber requirements that align with original equipment manufacturers (OEMs) and don’t break operations.

They also want faster, cleaner change control so construction continues even when standards or OEM designs shift. 

1) One EPC or EPCM: Single‑point vs. specialist subs with stronger performance on critical scopes.

  • Data center tie-in. Uptime depends on disciplined handoffs across protection, controls, and commissioning. A single EPC can simplify accountability, but EPCM can unlock better specialists for protection, battery energy storage system (BESS) integration, and controls—if interfaces are tightly managed.
  • Action. Use a living interface matrix with owner approval rights, a crisp RACI for every handoff, and time‑boxed escalation ladders so issues don’t linger.

2) Which performance guarantees actually protect uptime: Go beyond capacity; specify how fast and how clean the plant delivers power when IT load needs it.

  • Data center tie‑in. Contracts should protect “critical windows”—defined periods when workloads cannot drop. Require availability during those windows, start and response times, and PCC power quality (THD, flicker, voltage ride through).
  • Hybrid plants. Add duration, ramp-rate, and state-of‑charge guardrails, so capacity is available when the data center calls on it.

3) Keeping the schedule intact under utility and long-lead pressure: Treat utility engagement and long-lead items as critical path, not afterthoughts.

  • Data center tie-in. Delay at energization risks moving workloads or burning reserve capacity. Put utility witness tests, relay/protection reviews, and energization windows into the baseline schedule—not as “owner tasks.”
  • Action. Lock early procurement for transformers, switchgear, controls, and OEM field service. Use tiered liquidated damages that bite at commercial operation date slippage and failure to meet critical window operability, not just mechanical completion.

4) What’s a pragmatic OT security baseline: Segment critical control systems and control access, and make patching and incident response contractually real.

  • Data center tie-in. OT weaknesses can trip generation or storage when the data center most needs it. Physically and logically segment Energy Management Systems (EMS) and SCADA from BMS and corporate IT; enforce role-based access control and multifactor authentication for remote access.
  • Action. Require software bill of materials for control systems; set patching, vulnerability remediation, and incident response SLAs aligned to warranty/service obligations. Document tested backup/restore and secure configuration baselines.

5) How do we control change risk without freezing progress: Price predictable changes up front and keeps crews moving while commercials finalize.

  • Data center tie‑in. Utility standard updates, OEM redesigns, and cyber mandates arise mid-build. A “freeze and wait” approach burns schedule and risks critical windows.
  • Action. Use hybrid pricing (lump sum plus unit rates) with pre-agreed triggers for utility, OEM, and cyber changes. Run a rapid‑response protocol: issue provisional direction, field‑level holds limited by geography and time, and obtain target pricing in days, not weeks.

Print and share

Authors

Profile Picture
Partner
KKolton@perkinscoie.com

Notice

Before proceeding, please note: If you are not a current client of Perkins Coie, please do not include any information in this e-mail that you or someone else considers to be of a confidential or secret nature. Perkins Coie has no duty to keep confidential any of the information you provide. Neither the transmission nor receipt of your information is considered a request for legal advice, securing or retaining a lawyer. An attorney-client relationship with Perkins Coie or any lawyer at Perkins Coie is not established until and unless Perkins Coie agrees to such a relationship as memorialized in a separate writing.

312.263.2730

Explore more in

Home
Jump back to top